Maryland Moves the Key Bridge Rebuild Forward. Drivers Could Be Waiting Until 2030.

Aug 25
2 min read

The state is looking for a team to build the main span. In the meantime, traffic once carried by the bridge is crowding Baltimore’s two harbor tunnels.


BALTIMORE,  Crews are driving permanent foundation piles into the Patapsco River while Maryland looks for a team to build the most visible portion of the new Francis Scott Key Bridge. Above the water, progress can be measured in construction milestones. On the road, drivers are still measuring the loss of the old bridge in extra time spent getting across the harbor.


The Maryland Transportation Authority opened a competition on July 21 for the largest of four reconstruction contracts, covering the main span and the approaches over water. The first step is to review contractors’ qualifications. The teams that make the shortlist will then submit designs and prices. A separate contract to remove remaining pieces of the old bridge and perform other marine work is expected to go out for bids this summer.


When could the new bridge open?

Maryland is targeting late 2030 to reopen the crossing, about two years later than its initial projection. The state’s procurement plan calls for work on the land approaches to start in spring 2027 and construction under the main-span contract to begin that summer. Those dates are estimates. The transportation authority says the final construction schedule will take shape once it awards the contracts.


The new cable-stayed bridge is designed with a 1,665-foot main span and a system to protect its main piers from vessel strikes. The original bridge collapsed on March 26, 2024, after the container ship Dali struck one of its piers. The foundation work already underway can continue while the state selects the team that will build the span above it.


What the loss of the bridge has done to traffic

Before the collapse, the Key Bridge carried more than 30,000 vehicles a day, including more than 3,000 trucks. Losing that section of the southeastern Beltway pushed cross-harbor traffic toward the Fort McHenry Tunnel on I-95 and the Baltimore Harbor Tunnel on I-895, both of which already approached capacity during peak periods.


University of Maryland researchers found that the tunnels took on roughly 20 to 30 percent more traffic after the collapse. Short trips through the tunnel bottlenecks during the evening rush were still taking about 87 percent longer a year after the collapse than they had before it. That figure applies to the short trips researchers studied. It shows how losing one crossing can turn a quick trip into a much longer one when the remaining routes are already crowded.


For freight companies, the detour also depends on what a truck is carrying. Tunnel restrictions prevent many hazardous-material shipments and some larger vehicles from taking the most direct alternatives. A longer route can mean more fuel, more driver time and less room in the schedule for a late delivery.


Reopening the bridge would give drivers a third harbor crossing again. Until then, the tunnels will continue to absorb traffic that once had a way around them. The next contract award will give Maryland a clearer construction schedule. For commuters and businesses, the date that changes the daily calculation is the one when traffic can cross the Patapsco on I-695 again.


Recent Posts

See All

Comments


Top Stories

Stay informed with our latest news and updates. Subscribe to our newsletter for exclusive content and insights.

  • Youtube
  • Instagram
  • Facebook

© 2025 by YouHaveToListen. All rights reserved.

bottom of page